Client / Project |
Package / Scope of Work |
Year |
Tema
Oil Refinery (TOR) Ltd.
Sea Water
Intake
System,
Tema, Ghana
|
New
Seawater Intake Pump Station & Fibre Glass Pipeline from Harbor to the
Refinery Sea Water Basin |
2009 |
AHC
Mining Municipal Services Limited
Mine township Services Project,
Zambia
|
Rehabilitation of water treatment plants including old equipment like
clarifiers and filters at Chililabombwe and Luanshya Water Treatment
Works. |
2003 |
AHC
Mining Municipal Services Limited
Mine township Services Project,
Zambia
|
Pumping
Equipment and Associated Pipe works in Mufulira. |
2003 |
AHC
Mining Municipal Services Limited
Mine township Services Project,
Zambia
|
Rehabilitation of water treatment plants including old equipment like
clarifiers and filters at Kitwe, Kalulushi and Mufulira |
2003 |
National
Aluminum Company Ltd.
Industrial Drain Water Recycle System for CPP Expansion Unit 7,
Angul, Orissa |
Liquid
Waste Treatment Plant for treating effluents generated in the Captive
Power Plant (8x120 MW) for removal of suspended solids, oil, grease etc.
and achieving zero discharge by recycling total treated effluents back
to the plant.
|
2002 |
National Thermal Power Corporation Ltd.
4 x 210
MW Kahalgaon Super Thermal Power Project, Stage - I, Units 1, 2, 3 & 4,
Bihar, India |
Liquid
Waste Treatment Plant including network for collection of waste water
from coal settling pond, DM plant, Cooling tower blow down & PT Plant
Sludge de-watering etc. and subsequent treatment using lamella
clarifiers, complete with instrumentation for on-line measurement of
pollutants and ensuring compliance with pollution control norms.
|
1998 |
National Thermal Power Corporation Ltd.
3 x 210 +3 x 500 MW Korba Super Thermal Power Plant, Stage - I & II,
Units 1, 2, 3, 4, 5 & 6,
Madhya Pradesh. |
Ash Water
Recovery & Liquid Waste Treatment Plant comprising collection and
treatment of Coal Pile Run Off Wastewater, DM Plant Regeneration
Effluent, Filter Backwash Treatment, Pre-Treatment Plant backwash and
Sludge Treatment and Service Waste Water. Also included was the
auxiliary cooling water system inclusive of 4X 950 M3/hr cooling tower
|
1997 |
National Aluminum Co. Ltd.
Strip
Caster Project, Smelter Plant,
Angul, Orissa
|
Systems
for Twin Stream Water Filtration, Twin Stream Water Softening and
related Utility Piping. |
1997 |
National Thermal Power Corporation Ltd.
2 x 500
MW Rihand Super Thermal Power Station Stage - I, Units - 1, 2, 3 & 4,
Uttar Pradesh
|
Liquid
Waste Treatment Plant including piping network for collection of waste
water from coal settling pond, DM plant, Cooling Tower blow down etc.
|
1996 |
Bharat
Heavy Electricals Limited
NHVDC
Stage - I at MPEB Barsoor and Lower
Silery, Madhya Pradesh
|
15 M3/hr
Water Softening Plant including systems for Cooling Tower Chemical
Dosing, Chlorination System and Water Pumping & Piping. |
1996 |
I.G.
Mint
Calcutta
Modernization of IG Mint
Alipur, Kolkata, West Bengal |
Two
Stream 5 M3/hr Water Softening System, Two Stream 3 M3/hr DM Plant and
Raw Water Supply System including civil works |
1995 |